By Ye Guo
Longyuan Zhenhua participated in construction, created a world record of shortest construction period
On 28 December last year, as the last wind turbine joined the power grid and started to generate electricity, State Power Investment Corporation Jieyang Shen Quan 2 offshore wind power project full capacity connection to grid and power generation was realized. It is learnt that the project is the offshore wind power project of largest single installed capacity in the world for batch application. It is also one of the first batch of fair price offshore wind power projects in the grid. Jiangsu Longyuan Zhenhua marine engineering Co., Ltd., as the main contractor of Shen Quan 2 project, supported by various parties, after 215 days of work, realized start and completion of project in the same year, which created a world record of shortest construction period of over 500 MW wind farm.
The total installed capacity of Jieyang Shen Quan 2 offshore wind power project is 502 MW. 34 11 MW wind turbines and 16 8 MW wind turbines were installed. 1 220 kilovolt offshore booster station was built in support. Shen Quan 2 project joined the grid in time. Every year it can provide 1.743 billion kilowatts green electricity to Guangdong-Hong Kong-Macao Greater Bay Area, can satisfy the electricity demand of close to 900 thousand families in a year.
As the main contractor of Shen Quan 2 project, Jiangsu Longyuan Zhenhua marine engineering Co., Ltd. settled in Nantong in 2010. Apart from offshore wind power equipment foundation construction, equipment installation and maintenance, the company is also involved in construction and maintenance of submarine cable and marine engineering.